2018 Street and Water Main Replacements

In the summer of 2018, the Department of Public Works plans to improve the following areas:

Wilshire Street (Wildwood to Wilson)-0.20 miles: This project will replace the water main, including all valves and hydrants; remove and replace all curb/gutter and driveway aprons; remove and replace approximately 300 feet of storm sewer as well as making additional drainage improvements; and resurface the complete roadway. 

Birch Street (Bertoldo to 26th)-0.14 miles: This project will remove and replace all curb/gutter; make drainage and storm sewer improvements; and resurface the complete roadway.  

Sycamore Drive (Western to S. Arbor Tr.) and N. Arbor Tr. (Sycamore to first driveway)-0.20 miles: This project will remove and replace spot curb/gutter and resurface the complete roadway.

This work is scheduled to be completed in the Fall of 2018.